The
Tester Utilization
Tracking of the
Teradyne or HP Tester is done through tapping the signal
between the communication lines of these testers with a
handler that is attached.
Since the communication signal is streaming inward at the
flow rate of 96 Kbps, the signal must be process at high
speed to pickup the bin detail to distinguish between the
good yield and the reject bins.
The testing time and loading time will be time-stamped
immediately when the handler issue the command to request
the testers to pick up the unit to conduct the test. The
system will be able to capture up to 8 sites per test cycle.
Each test cycle can be calculated up to the accuracy of
1/100 seconds. For testers that can support dual-head, the
system can also capture the waiting time of one handler
while waiting for the other handler to finished its turn of
test. |
|

Teradyne Manufacturing
Test Platform |
 |
|
The
data can later be analyzed to provide information of the
following:
1. Through Put Time
- Indexing time (duration of the
Tester while waiting for the handler to
request for testing)
- Testing time (duration of the
Test cycle)
- Waiting time (duration of the
Handler while waiting for the other
handler to finish the
test)
2. Site Information
- Unutilized site – site which is
disable whether manually or by Load
Board program
- Low yield site – Site that
create rejects frequently
3. Yield Information
- Percentage of yield of individual
test site
- Percentage of yield of each Test
cycle
All the information above can be analyzed:
- by lot;
- by different type of handler used or;
- by program or load board used
that runs the production. This information can also be
viewed and analyzed in real-time.
|